Services for Wind Farms

Electrical connections to local DNO, interconnection of turbines, cable pulling and jointing

Recently Utility Installation Projects have diversified into working with the current influx in Wind Farm works around our coastline in the UK.

Our work with Wind Farms involves anything from the connections to local DNO (Distribution Network Operator) networks to the interconnection of turbines on land.

Utility Installation Projects also offer the usual full range of services including excavation work, duct laying, cable pulling and jointing on all Wind Farm projects.

This is an area of work Utility Installation Projects hope to explore more fully in the future.

See our case studies opposite for more information on our latest Wind Farm Projects

Case Studies

Scroby Sands Wind Farm, Great Yarmouth

Gt Yarmouth

Replacement of failed High Voltage cables from offshore wind turbines on beach.

These works involved the excavation of ...

Gunfleet Sands, Clacton

wind farms

On this project we installed marine cables from the beach at Clacton to the nearby EDF Sub Station.  The work involved ins...